PMI Project Management Professional Practice Question

True or False: If an activity has an Early Start (ES) of day 10, Early Finish (EF) of day 20, Late Start (LS) of day 12, and Late Finish (LF) of day 22, the float for this activity is 2 days.

  • False

  • True