PMI Project Management Professional Practice Question
The Work Breakdown Structure serves as a graphical depiction which showcases the deliverables-oriented hierarchy of the project, ensuring that all work of the project is accounted for.
False
True
The Work Breakdown Structure serves as a graphical depiction which showcases the deliverables-oriented hierarchy of the project, ensuring that all work of the project is accounted for.
False
True
The correct answer is that this statement is true. The Work Breakdown Structure (WBS) is indeed a graphical representation of the project's deliverables, organized hierarchically. It is designed to ensure that all the project's work components are identified and that no major deliverables are omitted. On the other hand, a backlog is commonly used in Agile methodologies and represents a list of items to be done, but it does not have the hierarchical structure that the WBS has.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Join premium for unlimited access and more features
All plans include the following perks.
Our pricing is simple. Full access to all certifications and exams, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
No annoying ads and popups. Study without distractions.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even more discounts than before.
Unlimited access to all PBQs and be prepared for the real thing.
Create an account or sign in to access our study materials.