PMI Project Management Professional Practice Question

The project manager for an infrastructure development project is preparing for an upcoming major deliverable review. The deliverable has to meet specific regulatory standards and customer quality requirements. Which of the following would be the MOST appropriate for the project manager to ensure that the deliverable is compliant and ready for the review?

  • Consult the quality metrics to verify that the deliverable adheres to defined quality standards.

  • Assess the impact of all approved change requests on the project's quality management plan.

  • Review the latest project management plan updates to check for any quality-related adjustments.

  • Analyze the latest quality reports to determine if the deliverables are functioning as intended.

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot