PMI Project Management Professional Practice Question
The Product Backlog is solely the responsibility of the Scrum Master.
False
True
We've got a new look! Please contact us if you run into any issues.
The Product Backlog is solely the responsibility of the Scrum Master.
False
True
The Product Backlog is primarily the responsibility of the Product Owner, not the Scrum Master. The Product Owner is accountable for maximizing the value of the product resulting from the work of the Development Team. The Scrum Master facilitates Scrum processes, coaches the team, and ensures that Scrum practices are adhered to, but the ownership of the Product Backlog - which includes its content, availability, and ordering - lies with the Product Owner .
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Join premium for unlimited access and more features
All plans include the following perks.
Our pricing is simple. Full access to all certifications and exams, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
No annoying ads and popups. Study without distractions.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even more discounts than before.
Unlimited access to all PBQs and be prepared for the real thing.
Create an account or sign in to access our study materials.