PMI Project Management Professional Practice Question
Project requirements should be prioritized based on the potential impact on project success and stakeholder value rather than solely on the ease of implementation.
True
False
We've got a new look! Please contact us if you run into any issues.
Project requirements should be prioritized based on the potential impact on project success and stakeholder value rather than solely on the ease of implementation.
True
False
Correctly prioritizing project requirements is essential as it ensures that the most critical aspects that could impact project success and deliver real value to stakeholders are addressed upfront. Prioritizing merely based on the ease of implementation might lead to significant needs being overlooked, which can adversely affect the project's outcome.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Join premium for unlimited access and more features
All plans include the following perks.
Our pricing is simple. Full access to all certifications and exams, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
No annoying ads and popups. Study without distractions.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even more discounts than before.
Unlimited access to all PBQs and be prepared for the real thing.
Create an account or sign in to access our study materials.