On a project with a Budget at Completion (BAC) of $500,000, the project team has planned to complete 45% of the work by the end of the third month. What is the Planned Value (PV) at the end of the third month?
Planned Value (PV) is calculated by multiplying the Planned Percentage Complete by the Budget at Completion (BAC). In this scenario, with a BAC of $500,000 and 45% of the work planned to be completed, the PV is 0.45 (or 45%) of $500,000, which equals $225,000. This means by the end of the third month, the project planned to have $225,000 worth of work completed.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does BAC mean in project management?
Open an interactive chat with Bash
How is Planned Value (PV) calculated?
Open an interactive chat with Bash
What is the significance of Planned Value in project management?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access