PMI Project Management Professional Practice Question

On a construction project, if the Late Start (LS) for the installation of fixtures is scheduled for day 25 and is expected to take 10 days, what is the Late Finish (LF) for this activity?

  • Day 35

  • Day 34

  • Day 24

  • Day 36

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot