Project Management Professional Practice Question

Midway through Sprint 3 of a mobile banking app, the product owner asks the team to introduce biometric login, a capability that was not part of the original release plan but promises higher customer adoption. According to the Agile Manifesto, what is the most appropriate next step for the team?

  • Freeze the project scope for the remainder of the release to avoid further disruptions.

  • Escalate the change to the project management office and wait for formal change control approval before acting.

  • Collaboratively refine and reprioritize the product backlog with the product owner so the team can accommodate biometric login in upcoming sprints while evaluating scope and schedule impacts.

  • Decline the request and keep the current sprint backlog unchanged until the next release cycle.

Project Management Professional
Agile
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot