Midway through a software-development project, the team finishes coding a new module. The project manager invites the product owner and key users to walk through the module against the documented acceptance criteria and records their sign-off. This activity will be repeated for each subsequent module to keep the work aligned with stakeholder expectations. Which Project Scope Management process is the project manager performing?
The project manager is performing Validate Scope. Validate Scope is the process of formalizing acceptance of completed deliverables with stakeholders. It is carried out periodically throughout the project to ensure the deliverables-and therefore the scope-remain aligned with stakeholder needs. Control Scope monitors the overall status of scope and manages baseline changes; Define Scope creates the detailed project scope statement; Collect Requirements gathers and documents stakeholder requirements before the scope baseline is set.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does 'project scope' mean?
Open an interactive chat with Bash
Why is stakeholder engagement important in project management?
Open an interactive chat with Bash
What are some common factors that can change project scope?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access