Project Management Professional Practice Question

Midway through a project to develop a new customer-facing mobile application, the marketing department submits a formal request to add a social-sharing feature that was not part of the original scope baseline. The project is currently on schedule and within budget. According to PMBOK best practices, what should the project manager do FIRST when this change request is received?

  • Revise the schedule and budget baselines and inform stakeholders after the feature is delivered.

  • Submit the request to the Perform Integrated Change Control process for impact analysis and approval.

  • Implement the feature if the team can complete it without needing additional funding.

  • Immediately reject the request to avoid scope creep and protect the existing schedule.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot