In the context of creating a Work Breakdown Structure (WBS), which of the following best illustrates the concept of decomposition?

  • Drafting the project schedule with milestones for deliverables completion as a breakdown or burndown chart

  • Assigning financial reserves to account for uncertainty in project costs

  • Dividing project deliverables into smaller tasks until they can be adequately managed and assigned

  • Assigning responsibilities and accountability for individual project deliverables

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot