In a project with 6 stakeholders, there are 15 potential communication channels.
False
True
PMI Project Management Professional
Process
Your Score:
Bash, the Crucial Exams Chat Bot
AI Bot
In a project with 6 stakeholders, there are 15 potential communication channels.
False
True
The statement is true. The number of communication channels is calculated using the formula N(N-1)/2, where N is the number of stakeholders. In this case, N = 6, so we have:
6(6-1)/2 = 6(5)/2 = 30/2 = 15
This formula accounts for bi-directional communication between each pair of stakeholders, without counting self-communication or duplicate channels. It's important for project managers to understand this concept to effectively plan and manage communication strategies, especially as the number of stakeholders increases. The number of channels grows quadratically with the number of stakeholders, which can significantly impact communication complexity in larger projects.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Join premium for unlimited access and more features
All plans include the following perks.
Our pricing is simple. Full access to all certifications and exams, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
No annoying ads and popups. Study without distractions.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even more discounts than before.
Unlimited access to all PBQs and be prepared for the real thing.
Create an account or sign in to access our study materials.