Free PMI Project Management Professional Practice Question

In a project network diagram, Activity B has two predecessors: Activity A with an Early Finish (EF) of 10, and Activity C with an EF of 15. What is the Early Start (ES) for Activity B?

  • 10

  • 15

  • 25

  • 5

This question's topic:
PMI Project Management Professional / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.