Free PMI Project Management Professional Practice Question
In a project, Activity B is dependent on the completion of Activity A. If Activity A has an Early Finish (EF) of Day 5 and Activity B has a duration of 3 days, what is the Early Start (ES) of Activity B?
The Early Start (ES) of an activity in CPM is determined by the Early Finish (EF) of its predecessor. Since Activity B depends on the completion of Activity A which finishes on Day 5, Activity B can start the next day. Therefore, the ES of Activity B is Day 6. Calculating ES involves recognizing that an activity's early start is the earliest time its dependencies allow it to begin.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does EF stand for in project management?
Open an interactive chat with Bash
What is the significance of dependencies in project management?
Open an interactive chat with Bash
Can you explain the Critical Path Method (CPM)?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional /
People
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features
Monthly
$14.99/mo
billed monthly (cancel any time)
3 Month Pass
$34.99
One time purchase Does not auto-renew.
Save $10!
MOST POPULAR
Annual Pass
$59.99
One time purchase Does not auto-renew.
Save $120!
BEST DEAL
Lifetime Pass
$119.99
One time purchase Good for life.
Save $240!
What you get:
Unlimited Questions
Major Voucher Discounts
Advanced PBQs
Zero ads
Track scores
Report Cards
Free tier is limited to 20 questions and limited Performance-based Questions (PBQs) .