Project Management Professional Practice Question
In a network diagram, Activity B has two predecessors: Activity A with an Early Finish (EF) of 10, and Activity C with an EF of 12. What is the Early Start (ES) for Activity B?
11
22
12
10
In a network diagram, Activity B has two predecessors: Activity A with an Early Finish (EF) of 10, and Activity C with an EF of 12. What is the Early Start (ES) for Activity B?
11
22
12
10
The correct answer is 12. The Early Start (ES) of an activity is determined by the latest Early Finish (EF) of its predecessors. In this case, Activity B has two predecessors: Activity A with an EF of 10, and Activity C with an EF of 12. Since we need to wait for both predecessors to finish before starting Activity B, we must use the later of the two EF values, which is 12. This ensures that all predecessor activities are completed before Activity B can begin. It's important to note that we don't add these values or use the earlier EF, as either approach would lead to an incorrect schedule.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.