PMI Project Management Professional Practice Question
In a network diagram, Activity B has two predecessors: Activity A with an Early Finish (EF) of 10, and Activity C with an EF of 12. What is the Early Start (ES) for Activity B?
11
22
12
10
PMI Project Management Professional
Process
Your Score:
Bash, the Crucial Exams Chat Bot
AI Bot