In a five-year infrastructure project, the project manager is tasked with setting up efficient management of project artifacts to ensure timely and easy access for all stakeholders. What is the most critical first step the project manager should undertake to guarantee effective management of these artifacts?
Decide when to distribute regular project status reports to stakeholders to ensure constant communication.
Establish why each type of artifact is necessary to support project goals and stakeholder requirements.
Identify what needs to be documented, including types of documents and data, which will serve as a basis for further artifact management decisions.
Determine who will have access to manage and update the artifacts, ensuring control and responsibility from an early stage.
Identifying what needs to be documented involves understanding and determining the specific types of artifacts required to manage the project effectively. It's essential as it informs the subsequent decisions on when, where, and who will manage these artifacts. Without determining what needs to be documented first, the manager cannot effectively plan other aspects such as storage locations or access permissions. Specifying why certain artifacts are needed can be inferred from this first step but is not the foundational action itself. On the other hand, deciding when to distribute reports is a related task that depends on what documentation exists and is more about communication rather than initial documentation requirement setup.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are some examples of project artifacts that might need to be documented in a project?
Open an interactive chat with Bash
How does identifying necessary project artifacts influence other project management decisions?
Open an interactive chat with Bash
Why is it important to establish what should be documented before deciding who has access to artifacts?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .