Free PMI Project Management Professional Practice Question

If an activity has a Late Start (LS) of day 5 and a Duration of 7 days, is the Late Finish (LF) day 12?

  • True

  • False

This question's topic:
PMI Project Management Professional / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.