Project Management Professional Practice Question
If a project's Earned Value (EV) is reported as $750,000 and the Actual Cost (AC) incurred is $800,000, what is the Cost Variance (CV) for the project?
-$50,000
$50,000
$750,000
-$25,000
If a project's Earned Value (EV) is reported as $750,000 and the Actual Cost (AC) incurred is $800,000, what is the Cost Variance (CV) for the project?
-$50,000
$50,000
$750,000
-$25,000
Cost Variance (CV) is calculated as CV = EV - AC. If the Earned Value (EV) is $750,000 and the Actual Cost (AC) is $800,000, then the Cost Variance (CV) would be $750,000 - $800,000, which equals -$50,000. This negative CV indicates that the project is over budget, as the costs incurred to achieve the earned value are higher than the value of the work performed.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.