If a project manager, while in the process of executing the project, realizes the team lacks a particular expertise required to complete an upcoming activity effectively, which of the following would be the BEST initial action in accordance with good practice within Project Resource Management?

  • Review the resource management plan for guidance on addressing the expertise gap and consider options such as training, hiring, or subcontracting to acquire the necessary expertise.

  • Proceed with the activity using current team members and capitalize on their ability to learn the necessary skills quickly during the execution of the activity.

  • Delay the activity until the next project phase while seeking an expert to join the project team.

  • Inform the project sponsor about the lack of expertise and request a decision on how to proceed.