Project Management Professional Practice Question

Halfway through a Waterfall project to implement a new ERP system, you compare the current stakeholder engagement assessment matrix with the target levels defined in the stakeholder engagement plan. Two department heads who were expected to be "supportive" are now classified as "resistant." No change requests have been submitted and existing communication channels remain the same. The schedule and cost performance are on track, and senior management expects minimal disruption. Which action should you take first to close the gap between actual and desired engagement?

  • Send out a general survey to all stakeholders to gather their satisfaction levels and broad feedback

  • Perform a root cause analysis to identify underlying issues with stakeholder engagement and adjust your strategies accordingly

  • Increase the frequency of stakeholder meetings tailored to each stakeholder's current engagement level

  • Focus on stakeholders who are already supportive and maintain current engagement practices with the others

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot