Free PMI Project Management Professional Practice Question

Given a project with the following activities and durations:

  • Activity A (Duration: 3 days, depends on no other activity)
  • Activity B (Duration: 5 days, depends on Activity A)
  • Activity C (Duration: 2 days, depends on Activity A)
  • Activity D (Duration: 4 days, depends on Activity B and Activity C)

What is the Early Finish (EF) for Activity D?

  • 11 days

  • 12 days

  • 8 days

  • 9 days

This question's topic:
PMI Project Management Professional / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot