PMI Project Management Professional Practice Question
During the process of sequencing activities for a construction project, the project manager has identified dependencies that are based on known best practices within the building industry. These dependencies are commonly referred to as:
External Dependencies
Internal Dependencies
Discretionary Dependencies
Mandatory Dependencies