PMI Project Management Professional Practice Question

During the process of closing procurements, one of the steps involves reviewing all documents to ensure that each contract is settled and closed out. Which of the following actions is most appropriate when closing project procurements?

  • Prepare and distribute the final project report to all stakeholders.

  • Collect procurement documentation and ensure that it is complete, indexed, and filed.

  • Update the risk register with new risks encountered during contract execution.

  • Conduct a final team meeting to release all project resources.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot