PMI Project Management Professional Practice Question
During the planning phase of a construction project, you have identified a potential shortage of skilled electricians due to high demand in the local market. What is the BEST action to include in your resource management plan to mitigate this risk?
Escalate the issue to senior management as it is likely to require delays or additional funds to secure skilled electricians in a difficult market.
Postpone any tasks requiring skilled electricians until the market conditions change.
Proceed with the current team and encourage team members to self-train on the needed electrical skills.
Incorporate training for available workers to enhance their electrical skills, and explore subcontracting opportunities to secure the necessary skilled electricians.