PMI Project Management Professional Practice Question

During the planning phase of a construction project, you have identified a potential shortage of skilled electricians due to high demand in the local market. What is the BEST action to include in your resource management plan to mitigate this risk?

  • Escalate the issue to senior management as it is likely to require delays or additional funds to secure skilled electricians in a difficult market.

  • Postpone any tasks requiring skilled electricians until the market conditions change.

  • Proceed with the current team and encourage team members to self-train on the needed electrical skills.

  • Incorporate training for available workers to enhance their electrical skills, and explore subcontracting opportunities to secure the necessary skilled electricians.

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot