During the planning phase of a construction project, you have identified a potential shortage of skilled electricians due to high demand in the local market. What is the BEST action to include in your resource management plan to mitigate this risk?

  • Incorporate training for available workers to enhance their electrical skills, and explore subcontracting opportunities to secure the necessary skilled electricians.

  • Proceed with the current team and encourage team members to self-train on the needed electrical skills.

  • Postpone any tasks requiring skilled electricians until the market conditions change.

  • Escalate the issue to senior management as it is likely to require delays or additional funds to secure skilled electricians in a difficult market.