During the initial phase of a project, you realize that there have been multiple instances of meetings starting late due to team members not joining on time. To address this behavioral issue going forward, what action should you take in accordance with establishing team ground rules?
Cancel or reschedule the meeting if key team members are not present at the scheduled start time.
Adjust the meeting times to start 15 minutes later to accommodate late attendees.
Convene a team discussion to collectively define consequences for tardiness to meetings.
Provide written warnings to team members who arrive late to meetings.