During the initial phase of a project, the project manager decides to evaluate the skills of the stakeholders to better align project roles with their capabilities. Which of the following methods would be MOST effective for accurately appraising the skills of stakeholders?
Organizing a group discussion with all stakeholders to observe dynamics and solicit skill-related feedback.
Conducting individual interviews with each stakeholder.
Reviewing the resumes and past project feedback of all stakeholders.
Sending out a standardized skills assessment form for stakeholders to fill out.