During the initial phase of a new construction project, you have identified a list of stakeholders that includes the client, the local government authorities, the project team, and the residents of the nearby community. Based on their level of interest and ability to impact the project, which of the following is the most appropriate way to categorize the local government authorities?

  • Low power, high interest stakeholders, because while they have an interest in the project's success, they can't significantly influence outcomes.

  • High power, high interest stakeholders, because they can influence project outcomes and are interested in the project's success.

  • High power, low interest stakeholders, because although they can impact the project, they generally have a low interest in the day-to-day progress.

  • Low power, low interest stakeholders, because their influence and interest in the project are minimal.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot