Free PMI Project Management Professional Practice Question

During the final phase of a large-scale software development project, you are reviewing the final deliverables to ensure they meet the initially agreed-upon project objectives. What is the most effective approach to verify that the objectives of the project agreement have been met?

  • Discuss with team members to gather feedback on whether the project meets the objectives.

  • Create a checklist that reflects the initially agreed project objectives to verify compliance with each point.

  • Compare the deliverables with those of previous similar projects to estimate objective fulfillment.

  • Wait for feedback from stakeholders after project delivery to understand if objectives were met.