Free PMI Project Management Professional Practice Question

During the execution phase of a project, you realize that an unexpected regulatory change will impact the project deliverables. According to company policy, all changes must align with the project's methodology. As a PMP, what is your best immediate next step in executing the change management strategy?

  • Communicate the regulatory change to the Change Control Board for assessment according to the established change management plan.

  • Continue with the execution as planned and deal with the regulatory change after project completion.

  • Inform the project team to halt all current activities until further notice.

  • Adjust the project's scope and schedule to comply with the regulatory change.