PMI Project Management Professional Practice Question
During the execution phase of a project, which of the following would BEST represent a potential threat to maintaining compliance with health and safety regulations?
Planning for upcoming organizational changes
Changes in project resource allocation that result in a shortage of personnel with health and safety management expertise
An organizational restructure that does not affect the project team composition
Budget cuts that force a reduction in project expenditures