PMI Project Management Professional Practice Question
During the execution phase of a project, which of the following would BEST represent a potential threat to maintaining compliance with health and safety regulations?
Planning for upcoming organizational changes
An organizational restructure that does not affect the project team composition
Changes in project resource allocation that result in a shortage of personnel with health and safety management expertise
Budget cuts that force a reduction in project expenditures