PMI Project Management Professional Practice Question

During the execution phase of a project, the project manager recognizes valuable insights that could enhance the performance of the current project as well as future projects. What is the BEST approach to ensure that this knowledge is captured and used effectively?

  • Document the insights in the lessons learned register and ensure they are reviewed and accessible for future projects

  • Email a summary of insights to all stakeholders at the end of the project

  • Wait until the project closure to record all insights and learnings

  • Discuss the insights in team meetings without formally recording them until the end of the project

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot