PMI Project Management Professional Practice Question

During the execution phase of a project, the project manager identifies a need to adjust resources to meet a revised project schedule. What is the BEST action for the project manager to take?

  • Hire more staff to meet the needs of the revised schedule.

  • Request all team members to extend their work hours until the project catches up to the revised timeline.

  • Assign additional tasks to available team members.

  • Update the resource management plan.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot