PMI Project Management Professional Practice Question
During the execution phase of a project, the project manager identifies a need to adjust resources to meet a revised project schedule. What is the BEST action for the project manager to take?
Update the resource management plan.
Hire more staff to meet the needs of the revised schedule.
Assign additional tasks to available team members.
Request all team members to extend their work hours until the project catches up to the revised timeline.