PMI Project Management Professional Practice Question

During the execution phase of a project, the project manager identifies a need to adjust resources to meet a revised project schedule. What is the BEST action for the project manager to take?

  • Update the resource management plan.

  • Hire more staff to meet the needs of the revised schedule.

  • Assign additional tasks to available team members.

  • Request all team members to extend their work hours until the project catches up to the revised timeline.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot