PMI Project Management Professional Practice Question

During the execution phase of a project, a new government regulation is announced that impacts the materials used in the project's product. What is the FIRST action a project manager should take to address the change in the project's external business environment?

  • Revise the project schedule and budget

  • Request additional funds to cover potential costs associated with the regulation

  • Inform all stakeholders about the new regulation

  • Assess the impact of the new regulation on the project scope/backlog

PMI Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot