PMI Project Management Professional Practice Question

During the execution phase of a construction project, you, the project manager, discover that the materials delivered do not meet the specifications outlined in the project scope. This has led to a critical issue affecting the structural integrity of the building. What should be your first step in collaborating with relevant stakeholders to resolve the issue?

  • Document the issue in the issue log and send it in the weekly status report to stakeholders.

  • Instruct the project team to halt all construction activities until new materials are delivered.

  • Organize an urgent meeting with the suppliers, your quality control team, structural engineers, and the client to discuss the issue and potential solutions.

  • Issue a change request to replace the substandard materials.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot