PMI Project Management Professional Practice Question

During the execution phase of a construction project, you, the project manager, discover that the materials delivered do not meet the specifications outlined in the project scope. This has led to a critical issue affecting the structural integrity of the building. What should be your first step in collaborating with relevant stakeholders to resolve the issue?

  • Organize an urgent meeting with the suppliers, your quality control team, structural engineers, and the client to discuss the issue and potential solutions.

  • Document the issue in the issue log and send it in the weekly status report to stakeholders.

  • Instruct the project team to halt all construction activities until new materials are delivered.

  • Issue a change request to replace the substandard materials.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot