PMI Project Management Professional Practice Question

During the execution phase of a construction project, the project manager observes that the scheduled completion date might slip due to an unexpected delay in regulatory approval for a building extension. What should the project manager do first to manage this newly identified risk?

  • Wait to see if the regulatory approval will indeed cause a delay before taking any action.

  • Reschedule all work to a later date based on the assumption that the delay will occur.

  • Increase resources in other areas to compensate for the potential delay.

  • Update the risk register to include the new risk, its potential impacts, and propose risk response strategies.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot