Project Management Professional Practice Question

During the execution phase of a construction project, a quality audit reveals that a batch of installed fixtures does not fully comply with the specified quality standards. While these fixtures are functional, their lower quality poses a risk of premature failure and increased long-term maintenance costs. What is the BEST course of action for the project manager to take?

  • Immediately replace the non-compliant fixtures using project contingency reserves.

  • Create a change request to address the non-compliance with the quality standards.

  • Accept the risk of premature failure to avoid impacting the project schedule.

  • Note the quality gap in the lessons learned register and address it during the project closure phase.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot