During the execution of an IT infrastructure upgrade project, you have identified a mix of internal and external stakeholders with varying degrees of power and interest. Which of the following steps would be MOST effective for your next action to ensure a robust stakeholder engagement strategy?
Send out weekly project updates via a newsletter to all stakeholders to keep them informed of project progress and decisions.
Review the stakeholder engagement plan to ensure it aligns with the latest project schedule and communication frequency.
Schedule a one-time meeting with all stakeholders to obtain their buy-in and then focus solely on the project execution.
Develop and implement a tailored engagement plan for each category of stakeholders and periodically validate its effectiveness through feedback and stakeholder responses.
After analyzing and categorizing stakeholders, it is crucial to tailor the engagement strategy to their specific categories and then develop, execute, and validate this strategy. Validation implies confirming that the strategy effectively engages stakeholders as planned and is bringing anticipated results such as resolving concerns, getting support, and valuable input. Simply reviewing the stakeholder engagement plan or sending out general project updates would not provide evidence of its effectiveness in actual engagement. Communication should be an ongoing process tailored to the stakeholders' needs and influence.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why is it important to categorize stakeholders by power and interest?
Open an interactive chat with Bash
What is the purpose of validating the stakeholder engagement strategy?
Open an interactive chat with Bash
How can feedback be collected to validate the engagement strategy?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .