Project Management Professional Practice Question

During the execution of a software development project, the change control board (CCB) approves a request that adds significant new functionality. What is the project manager's most appropriate initial action regarding the project schedule?

  • Immediately update the schedule baseline to reflect the change.

  • Analyze the impact of the new functionality on the existing schedule.

  • Inform stakeholders that the project's end date will be delayed.

  • Apply schedule compression techniques to accommodate the new work.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot