During schedule analysis you discover that two mechanical engineers are assigned to three critical-path activities at the same time, creating a clear overallocation. You decide to apply the resource-optimization technique known as resource leveling. Which statement accurately describes the potential impact of resource leveling on the project schedule?
It preserves the original finish date by adjusting only non-critical activities within their float.
It cannot change the critical path but evens out resource usage inside the existing schedule baseline.
It is used only when a fixed, immovable deadline is the project's highest priority.
It may delay activities on the critical path and extend the project completion date in order to remove overallocation.
Resource leveling balances demand with the available supply of resources by adjusting activity start and finish dates. Because activities may be delayed beyond their total float, leveling can consume float, shift the critical path, and extend the overall project completion date. Resource smoothing, in contrast, adjusts only non-critical activities within their float and therefore keeps both the critical path and the finish date unchanged.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is resource leveling in project management?
Open an interactive chat with Bash
How does resource leveling differ from resource smoothing?
Open an interactive chat with Bash
Why is it important for project managers to understand the implications of resource leveling?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access