Project Management Professional Practice Question

During schedule analysis you discover that two mechanical engineers are assigned to three critical-path activities at the same time, creating a clear overallocation. You decide to apply the resource-optimization technique known as resource leveling. Which statement accurately describes the potential impact of resource leveling on the project schedule?

  • It preserves the original finish date by adjusting only non-critical activities within their float.

  • It cannot change the critical path but evens out resource usage inside the existing schedule baseline.

  • It is used only when a fixed, immovable deadline is the project's highest priority.

  • It may delay activities on the critical path and extend the project completion date in order to remove overallocation.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot