During release planning for a new customer-facing web portal, the sponsor urges the team to start with the "quick-win" features because they can be coded fastest. To follow good practice for maximizing stakeholder value, what factor should drive the order in which requirements are implemented?

  • Estimated development effort and technical complexity alone

  • Expected business value and impact on project objectives

  • Sequence in which stakeholders originally submitted their requests

  • Implementation order proposed by the technical lead to minimize refactoring

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot