During project execution, the following data are available:

  • Budget at completion (BAC): 1,200,000 USD
  • Cost performance index (CPI): 0.80
  • Management believes that the cost performance achieved to date will continue unchanged for the remainder of the work.

Based on Earned Value Management practice, what is the current Estimate at Completion (EAC) for the project?

  • 1,800,000 USD

  • 1,200,000 USD

  • 960,000 USD

  • 1,500,000 USD

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot