Project Management Professional Practice Question

During project execution, a team member submits a change request that would increase the budget slightly but add functionality the customer values. According to PMI-recommended change-control practices, what should the project manager do FIRST?

  • Document the request, analyze its impact with the team, and submit it through the integrated change-control process.

  • Escalate the request directly to the sponsor because only high-level stakeholders can initiate cost-related changes.

  • Reject the request to avoid scope creep and instruct the requester to resubmit the idea after project closure.

  • Implement the change immediately to capture the added business value since the impact is minor.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot