PMI Project Management Professional Practice Question

During project execution, a project manager notices that some project activities are deviating from the project management plan. What should be the BEST step to ensure that the project remains aligned with the project's performance objectives?

  • Wait until the next project status meeting to discuss the deviations with the team

  • Immediately inform all stakeholders about the deviations and seek their input on how to proceed

  • Review and analyze performance data to identify the necessary corrective or preventive actions

  • Stop all project work until the project management plan can be reevaluated

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot