During negotiations to finalize a project agreement, the project manager observes that both the internal team and an external vendor appear generally satisfied with the draft terms. Which action should the project manager take before moving forward?
Document the perceived consensus and seek executive approval without further analysis.
Move directly to contract signing to avoid prolonging discussions.
Assess and confirm each party's priorities and ultimate objectives before finalizing the agreement.
Shift focus to relationship-building activities because the terms already appear acceptable.
Even when all parties seem to agree, best practice requires the project manager to confirm each side's priorities and the ultimate objectives of the agreement. This step prevents hidden assumptions or unmet expectations from surfacing later and aligns the negotiated terms with the project's goals. Skipping the validation could leave ambiguities that jeopardize delivery or stakeholder satisfaction.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why is it important to assess priorities during negotiations?
Open an interactive chat with Bash
What are ultimate objectives in a project agreement?
Open an interactive chat with Bash
What can happen if priorities and objectives are not clearly defined?
Open an interactive chat with Bash
Project Management Professional
People
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access