Project Management Professional Practice Question

During initiation of a cross-functional product-development project, the project manager maps each stakeholder on an influence-impact grid and evaluates how team members' positions in the organization could affect key decisions. According to PMI best practices, what is the primary reason for performing this influence analysis at this stage?

  • To identify individuals who can drive project success and engage them effectively

  • To assign work packages strictly based on staff availability

  • To record stakeholders' personal hobbies for team-building activities

  • To determine the exact duration of each activity for the project schedule

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot