Project Management Professional Practice Question

During an infrastructure project, the project manager wants to ensure that shifts in market trends do not unexpectedly expand or reduce project scope. According to PMI guidance, how should the project manager approach surveying market trends?

  • Assign the task to a compliance officer after planning is completed and revisit only if a stakeholder requests.

  • Perform a single analysis during project initiation and lock the scope baseline afterward.

  • Delay market-trend analysis until the closing phase to capture lessons learned for future projects.

  • Continuously monitor market trends throughout the project life cycle and adapt scope if needed.

Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot