During an agile project's retrospective, the team has identified several possible improvements for their process. Which of the following actions would BEST align with the agile principle of continuous improvement?
The Product Owner chooses the most critical improvements.
The team implements all identified improvements at once to maximize the chances of process enhancement.
The team prioritizes improvements that have the longest tradition in the company, respecting the established practices.
The team selects only a few improvements to focus on based on the team's capacity to address in the next iteration, planning to measure the outcomes for validation.